Supervision of the Project for the Rehabilitation of Treated Water Transmission Line from Manfouha Plant to Al-Amaaria – Phase I

Client Saudi Irrigation Organization
Section Supervision
Project Date 2023
Description

supply of ductile iron pipes of class (k9) head and tail and high-density polyethylene pipes with lengths of up to 89 km and the necessary concrete rooms for air and washing valves, control and insulation valves and beneficiary outlet valve rooms, to cover the needs of various crops for beneficiaries from organizations and individuals, as the network will supply irrigation water to cover areas with an area of approximately 12,600 hectares and a total irrigation water quantity of 110,000 m3/day and a number of 219 beneficiaries